Optima Engineering PA
Optima Engineering, P.A.
1927 South Tryon Street STE 300
Charlotte, NC 28203
Phone: 704-338-1292
Email info@optimapa.com
Commissioning Projects
Wachovia – West End Center, Winston-Salem, NC (Multiple Projects):

(Presently consists of approximately 100,000 SF of computer raised floor area with mechanical, electrical,  plumbing and fire protection support systems.)

UPS System 1 and Generator Plant Installed 3-750 kVA static UPS modules and system control cabinet.
Generator Plant Installed 3-1250 kW generators and paralleling board.
Generator Plant Expansion Added 1-1250 kW generator.
UPS System 1 Expansion Added 1-750 kVA static UPS module.
UPS System 2 Addition Added 2-750 kVA static UPS modules and a second system control cabinet.  Also added mechanical, plumbing and fire protection support systems.
5th Generator Addition Added 1-1750 kW generator.
UPS System 3 Addition Installed 3-750 kVA static UPS modules and system control cabinet.


Wachovia – Distribution Utility Center, Charlotte, NC (Multiple Projects):

Infrastructure Upgrade Removed existing single utility service, single generator and single static UPS module and replaced with dual 4000A utility services, 3-1500 kW generators and a system control cabinet with 2-750 kVA rotary UPS modules.
Existing Building Addition Approximate 120,000 SF addition with associated mechanical, electrical, plumbing and fire protection support systems.  Added a system control cabinet with 2-750 kVA rotary UPS modules.


Time Warner Cable – Main Data Center, Charlotte, NC (Multiple Projects):

Infrastructure Upgrade The 10,000 SF of computer raised floor required the removal of the existing single utility service and addition of dual 4000A utility services, 2-2000 kW generators and a system control cabinet with 3-300 kVA static UPS modules.  A glycol loop was installed for cooling in the data center and mission critical areas with redundant computer room AC units and roof-top dry-coolers and pumps.  An FM-200 fire extinguishing system and pre-action sprinkler system was installed in the data center as well as pre-action  sprinkler systems in other mission critical areas.
UPS System Expansion Added 1-300 kVA static UPS module.



Hewitt Call Center, Charlotte, NC:

Converted approximately 170,000 SF of shell building space into a call center with a 3,500 SF Data Center. Installed 2-225 kVA static UPS modules for the Data Center.  Installed 1-500 kVA static UPS module to provide an additional layer of redundancy for the Data Center as well as serve the Call Center. 

The Data Center, associated HVAC and building HVAC are backed up by 2-1750 kW generators.


Silas Center, Winston-Salem, NC:

Converted approximately 170,000 SF